Removal of the roof skylights and replacement of the roofing material and ventilation upgrade.

98 Allison Crescent, Menai - behind Menai Shopping Centre.

Project timeline

Project start:  early 2025

Expected completion:   end of 2025

Information update

Project background

The Indoor Sports Centre has been subject to ongoing roof leaks and progressive repairs to the roof have been unsuccessful.  The roof renewal works will ensure the roof is completely watertight and the improved ventilation will minimise internal condensation.

Project scope

The replacement of roofing will include the removal of skylights and an upgrade of the ventilation system.  Above the playing courts new insulation will be installed.  The planned work will include:

  • Removal and disposal of existing roof sheets, skylights and insulation
  • Installation of new roof sheets, insulation and associated works
  • Installation of new ventilation
  • Sealing of eaves, soffits and verges
  • Provide a complying roof access system.

Project schedule

During the design process it has been discovered that the roof structure does not have the capacity to support the additional load of the ventilation system.  This prevented work on site starting on the scheduled date as a development application is required. A solution to support the mechanical equipment has been developed and a design completed.

The project timeline has been extended due to the redesign and a Development Consent has now been received.

After the initial site establishment works in March, the reconstruction is scheduled to begin in May, and the work plan ensures that two basketball courts will remain available for use during the construction period.  For safety reasons, access may be restricted during specific activities, such as craning materials onto the roof.  These disruptions will be minimized and scheduled to reduce inconvenience.  The project timeline includes:

  • Development Application submitted (new design) - September 2024 (complete)
  • Development Consent issued – December 2024 (complete)
  • Site Establishment – March 2025
  • Expected commencement of reconstruction - May 2025
  • Expected Practical Completion – end of 2025

Impacts during construction

  • There will be disruptions to sporting activities in order to provide a safe environment for everyone.
  • Council Sport Services will work closely with the impacted sporting clubs and the Centre Manager to minimise disruptions to sporting fixtures wherever possible.

We appreciate your patience and understand that this work will have an impact on the public while we carry out the remainder of these essential works.

Funding

This project is fully funded by Sutherland Shire Council.