5 Coolidge Crescent, Bonnet Bay

Project timeline

Project start:  Sept 2024

Expected completion:   Dec 2024

Project background

We are excited to let you know that Council will be renewing the irrigation system at Lakewood City Oval which forms part of a larger recreation precinct.

The installation will enable the continuation of sporting competitions, training and will improve the overall experience for our community and visitors to this precinct.

This irrigation renewal is important to ensure the longevity and quality of the playing surface throughout the season.

Project scope

The work include:

  • Supply and installation of an automatic irrigation system.
  • Includes smart controls for irrigation and monitoring.
  • Trenching of oval and turf remediation.

Project schedule

Detailed Design - December 2023 (complete)

Tender - February 2024 (complete)

Site Establishment – September 2024

Practical Completion – end of December 2024  (weather permitting)

Impacts during construction

The playing field will be closed during construction.  The tennis courts, clubhouses, cricket nets, playground and car parking areas will remain open.

We are working with the local community groups to make suitable arrangements for training and competition matches during this important work.

We appreciate the support and collaboration of our sport clubs and local user groups during this process.

We will keep you updated as the work progresses and thank you for your patience.

Funding

This project is fully funded by Council.