Critical Water main renewals - Kingsway, Cronulla

Works start date: Jul 2017

Works end date: Oct 2017

Works location: Kingsway, Cronulla View on map

Reason for works

Sydney Water is renewing sections of water main along the Kingsway, Cronulla, from the intersection of Croydon Street to Elouera Road. This  essential work will help to improve the reliability of the local water supply.

Scope of works

Stage One: Water main renewal
 

• setting up traffic control and lighting
• Saw cutting and digging in the roadway  
• disconnecting the existing water main
• laying and new water main. 

 

Stage Two: Connections

• connecting new water main to Sydney Water network.

 

Project schedule

Stage One: Water main renewal

Work is planned to start on 24 July 2017 and is expected to be completed in five weeks, weather permitting. Night work hours will be from 8pm to 5am Sunday to Thursday. Work on Friday and Saturday night will be scheduled only when required.

 

Stage Two: Connections

Work will commence once stage one is complete,  and is expected to be completed October 2017, weather permitting.

 

Public impacts during construction

Sydney Water's contractor Comdain will establish a temporary compound at 44 Denman Ave Woolooware. This location will be used as a storage area for machinery, materials, pipes and fittings. 

The compound will be established on Wednesday 19 July and will remain in place until October 2017, weather permitting. 

 

Stage One: Water main renewal

This stage of work will not affect the water or waste water services.

Construction work will involve increased noise, dust and truck movements. To avoid any impacts we suggest that you try to keep windows and doors closed if your business or property is in close proximity to the work.

The roadway and disturbed areas will be temporarily restored each night to allow for continued use during the day. When all work is complete, Sydney Water will liaise with Council to permanently restore disturbed areas. 

 

Stage Two: Connections

The water supply will need to be interrupted to connect the new main and property Services. Night work will be required to complete this work. Affected residents will be notified by Sydney Water prior to this happening. 

 

Traffic and pedestrian management controls will be in place to ensure public safety.
Sydney Water will make every effort to minimise any impact this work may have on the community.

Enquires regarding these works can be directed to Comdain’s Community Relations line on 8203 6299 or 0417 259 406 or email nswcommunity@comdain.com.au.

For 24 hour service difficulties or emergencies, please call 13 20 90.

More information

Enquiries

or

Did this page help you?

We monitor feedback and will respond to your comments if you include your email address.



Please type the characters you see in the picture below

Please type the code in the box above