Tonkin Oval Boat Ramp and Pontoon Upgrade

Reconstruction of the boat ramp and installation of a floating pontoon.

Works start date: Jun 2019

Works end date: Oct 2019

Documents / Plans: Design Layout.pdf
Boatramp Sections.pdf
Site Sign - Boat Ramp Upgrade.pdf (6.2MB)

Works location: Tonkin Street, Cronulla (near the Oval) View on map

Scope of works

The works for Stage 1 include:

  • Construction of a new boat ramp to modern standards.
  • Demolition of existing boat ramp
  • Installation of a pontoon suitable for small craft.
  • Dredging as required to undertake boat ramp and pontoon construction. 

The future reconfiguration of the car park will form Stage 2 of this project.

Project schedule

The expected delivery milestones are:

  • Concept design - Apr 2016.   Completed
  • Community Consultation - May to Nov 2016.   Completed
  • Detail Design - Jan 2017 to Nov 2018.   Completed
  • Approvals - Nov 2018.   Completed
  • Tender - Nov 2018 to May 2019.   Completed
  • Site establishment - mid June 2019 - Completed
  • Expected project completion - Oct 2019 - Completed

Stage 2 - Reconfiguration of the car parking area - subject to funding and approvals.

Funding

This project is funded by Section 94 contributions and Transport for NSW ‘Boating Now’ program and the Maritime Infrastructure Delivery Office.

More information

Enquiries

or

Did this page help you?

We monitor feedback and will respond to your comments if you include your email address.



Please type the characters you see in the picture below

Please type the code in the box above