Scylla Bay Boat Ramp, Pontoon and Car Park Upgrade

Reconstruction of the boat ramp, pontoon and upgrade of the adjacent car parking area.

Works start date: Jan 2016

Works end date: May 2018

Documents / Plans: Site Signage 2017.pdf
Consultation Data Sheet - 2015.pdf

Works location: Verona Range, Como (near Oval and Rowing Club) View on map

Scope of works

The works include:

  • Construction of a new boat ramp to modern standards.
  • Installation of a floating pontoon suitable for small craft.
  • Reconfiguration of the car park to better suit current uses.
  • Dredging as required to undertake boat ramp and pontoon construction.

Project schedule

The delivery milestones are:

  • Concept design: May 2016  - Complete
  • Community Consultation: Waterways Assets (RMS Boating Now Program) June 2016 - Complete
  • Community Consultation Detailed Design for Scylla Bay: Nov 2016 - Complete
  • Design Finalisation: Jan / Feb 2017 - Complete

Boat Ramp & Wharf Construction

  • Tender: March 2017 - Complete
  • Approvals: March 2017 - Complete
  • Procurement: May / July 2017  - Complete
  • Award of Contract: August 2017 - Complete
  • Site establishment: Sept 2017 - Complete
  • Expected practical completion: Feb 2018 - Complete

This boat ramp and new floating pontoon are now open for everyone to use.

 

Car Park Upgrade

These works will commence upon completion and site dis-establishment of the compound area.

  • Preparation of sub-base
  • Installation of driveway laybacks
  • Asphalt surfacing
  • Minor landscaping works - end May 2018

 

Public impacts during construction

  • The boat ramp will closed during construction works. Users can put in at alternate ramp sites at Connell Road, Oyster Bay; Washington Drive, Bonnet Bay; or Prince Edward Park.  The ramp at Burnum Burnum Sanctuary is upgraded and now open for use.
  • Vehicle parking will be limited during the construction phase.
  • There will be additional traffic on Verona Range.
  • There may be an increase in dust and noise from time to time, as we upgrade these facilities.

We appreciate the patience of adjacent residents and frequent users of the existing facility, while we deliver this upgrade.

Funding

This project is funded by Section 94 contributions and Roads and Maritime Services grant funding under their ‘Boating Now’ program.

More information

Enquiries

or

Did this page help you?

We monitor feedback and will respond to your comments if you include your email address.



Please type the characters you see in the picture below

Please type the code in the box above