Cronulla Town Centre Public Domain Master Plan

Council is preparing a Master Plan aimed at improving the Cronulla Town Centre public domain. The Cronulla Town Centre Public Domain Master Plan is a design framework that will help us work towards a better Cronulla. It provides Council and the community with an idea of how the area might look in the future and what needs to be done to get there

Works start date: Jul 2016

Works end date: Dec 2017

Documents / Plans: Study Area Map.pdf

Works location: View on map

Background

Council is committed to working with the community throughout the process of public domain improvement in Cronulla. The Cronulla Public Domain Master Plan is the next major step in this process. The Master Plan:

  • builds on the fresh ideas generated by the 2014 Cronulla Design Ideas Competition
  • works toward achieving the goals established in the subsequent Cronulla Public Domain Strategy
  • addresses ongoing challenges surrounding traffic, parking, pedestrian movement and the amenity of the Cronulla Plaza.

Council has engaged a specialist consultant team led by Gallagher Studio to prepare the Master Plan and to fully engage with the community. Community engagement for the project commenced in November 2016 and is ongoing.  See below for details on how you can be involved.

Purpose

The purpose of the Master Plan is to facilitate a more connected and vibrant Cronulla Centre, recognising Cronulla's importance as a town centre and visitor destination.

Objectives

The objectives of the Master Plan are to:

  • maintain and enhance Cronulla's distinctive place qualities
  • support Cronulla's role as a town centre and important visitor destination
  • enhance the amenity and accessibility of the Cronulla Centre's public domain
  • provide a comprehensive approach to the long-term development of the public domain within the Cronulla Centre

    Outputs

    The Master Plan will:

    • produce an overall design concept to enhance Cronulla Centre’s public domain
    • contain proposals to improve local area traffic management and parking
    • inform future detail design and construction of public domain works

      Timetable

      Stage 1 - Research and Analysis (completed)

      Aug/Sep 2016 - A detailed understanding of Cronulla is gained through research and analysis.

      Stage 2 - Principles and Ideas (completed)

      Sep/Oct 2016 - Principles and ideas to guide the Master Plan are developed.

      Oct/Nov 2016 - Community consultation on '7 Guiding Principles' and '7 Big Ideas'.

      Stage 3 - Draft Master Plan (completed)

      Nov 2016/Aug 2017 - The draft Master Plan is prepared. Council to endorse public exhibition.

      Stage 4 - Public Exhibition

      Sept 2017 - The draft Master Plan is exhibited and the responses of the community are received.

      Stage 5 - Final Master Plan

      Oct -Dec 2017 - The draft Master Plan is finalised in response to community feedback.  The final Master Plan is presented to Council for endorsement.

      Funding

      This project is funded by Sutherland Shire Council from the Shopping Centres Upgrade Program.

      Have Your Say

      Your feedback on the draft Cronulla Public Domain Master Plan can help shape Cronulla's future.  We welcome your thoughts and comments on the draft Master Plan,which is on public exhibition  1 - 30 September. 

      Click through to have your say


      More information

      Enquiries

      or

      Did this page help you?

      We monitor feedback and will respond to your comments if you include your email address.



      Please type the characters you see in the picture below

      Please type the code in the box above