Cronulla Rock Pool Upgrade

Upgrade the entry, and removal of the wave ramps to reduce sand infilling.

Works start date: Apr 2016

Works end date: Oct 2017

Works location: The Esplanade - 16R Ozone Street, Cronulla View on map

Project schedule

The works are to be scheduled during Autumn / Winter season to minimise disruption to pool users.

The delivery milestones for Access Stairs include:

  • Concept Design - February 2015 - Completed
  • Construction Design Drawings for Access Stairs - Apr 2016 - Completed
  • Reconstruction of Access Stairs - July/Aug 2016 - Completed

The delivery Milestones for the Wave Ramp Removal include:

  • Commission Specialist Report to assess the continued sand siltation - July 2013 - Completed
  • Decision undertaken to remove the ramps - Dec 2013 - Completed
  • Procurement process - 2016 - currently under way.

Funding

This project is funded by Sutherland Shire Council.