Cassandra Crescent Reserve, Heathcote – Playground Renewal

Installation of new play equipment.

Works start date: Nov 2020

Works end date: Dec 2020

Documents / Plans: Site sign.pdf

Works location: 33R Cassandra Crescent, Heathcote. View on map

Reason for works

Council is excited to announce the construction of a renewed playspace in Cassandra Crescent Reserve.  Council will be delivering this new play space for the enjoyment of the community by the end of 2020.

The new playground will be replaced in the same location within the reserve.

Scope of works

The playspace will be renewed with upgraded equipment and landscape works, including:

  • Play equipment for a variety of ages.
  • A nature play area for informal play.
  • Provision of a concrete path around the playground.
  • New table and bench seats.

Project schedule

The delivery milestones for this project are: 

  • Design – July 2020 - completed
  • Approvals – July 2020 - completed
  • Procurement of playground equipment – July 2020 - completed
  • Appointment of landscape contractor – October 2020 - completed
  • Community notification via letterbox flyer – October 2020 - in progress
  • Site establishment for construction - early November 2020
  • Expected project completion – end December 2020

Public impacts during construction

The playground will be closed during the reconstruction phase.  There will be some construction noise during the demolition and installation of new equipment and path construction. 

We apologise for any inconveniences this may cause and thank you for your patience and understanding while we carry out these works.

Funding

This project is fully funded by Council.

More information

Enquiries

or

Did this page help you?

We monitor feedback and will respond to your comments if you include your email address.



Please type the characters you see in the picture below

Please type the code in the box above