Burnum Burnum Sanctuary - Boat Ramp Upgrade

Upgrade of the existing boat ramp providing access to the Woronora River. This work includes provision of a floating pontoon, refurbishment of the wetland and Upgrade to the car parking area.

Works start date: Apr 2017

Works end date: Jul 2017

Documents / Plans: Project Fact Sheet.pdf
Layout Plan.pdf

Works location: River Road, Woronora (access to Reserve via the low level Woronora Bridge) View on map

Project schedule

Stage 1 -  Boat Ramp Upgrade - Scheduled to commence April 2017

  • Demolish existing ramp  -  Week 2
  • Construct new ramp, desilt pond 1, new pipe connection to pond 2  -  Week 8
  • Install pontoon, & new weir in wetland  -  Week 14
  • Site reinstatement  -  Week 16

 

Stage 2 - Carpark Upgarde - Will commence July2017

  • Provision kerb & associated footpath works
  • Drainage works
  • Pavements resurfacing
  • Linemarking and associated Landscape works

Funding

This project is jointly funded by RMS under their 'Boating Now' program and Sutherland Shire Council.