Ascot Place Reseve, Miranda - Playground Renewal

Installation of play equipment.

Works start date: Apr 2020

Works end date: May 2020

Documents / Plans: Site Sign.pdf (2.0MB)
Community Notification Flyer.pdf

Works location: 43-45 Miranda Road, Miranda - with dual access from Ascot Place View on map

Reason for works

Council is excited to announce the construction of a renewed play space.  The new playground and fitness areas will occupy a similar location to the existing play space, within the Reserve.

Scope of works

The new works include:

  • Play equipment for a variety of ages.
  • Provision of concrete path & sandstone wall around the playground.
  • Levelling the concrete path to allow access to both play zones.
  • Installation of fitness equipment and new synthetic surface below.
  • Shade structure to part of the play space.
  • Installation of new seat.
  • Provision of drinking & bottle filler station.
  • Installation of new solar panel light and Park signage.

Project schedule

The delivery milestones for this project are:

  • Concept design – Sept 2019 - completed
  • Community Consultation – Dec 2019 to Feb 2020 - completed
  • Detail Design – Nov 2019 - completed
  • Approvals – Nov 2019 - completed
  • Tender – Dec 2019 - completed
  • Site establishment – April 2020
  • Expected project completion - May 2020

Public impacts during construction

The playground will be closed during the reconstruction phase and there will be minimal noise during the removal and installation.

 We apologise for any inconvenience.  Thank you for your patience and understanding while we carry out these works.

Funding

This project is fully funded by Council

More information

Enquiries

or

Did this page help you?

We monitor feedback and will respond to your comments if you include your email address.



Please type the characters you see in the picture below

Please type the code in the box above